| Shift | B |
|---|---|
| Furnace | Furnace II |
| Date | 02 May 2021 |
| MWH | 39.7 |
| MVAH | 46.9 |
| PF | 0.84 |
| Tap Change Reading | 12733 |
| No of tap changing | 32 |
| Paste Level - E1 | 4.4 |
| Paste Level - E2 | 4.45 |
| Paste Level - E3 | 4.5 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 1 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 200 |
| Slipping - E2 | 150 |
| Slipping - E3 | 200 |
| CRO | Kapansula |
| Total No. of Batches | 78 |
| Plant 66kv kvah | 0 |
| Shift Incharge | shrikanta |