| Shift | A |
|---|---|
| Furnace | Furnace I |
| Date | 14 Apr 2026 |
| MWH | 38.3 |
| MVAH | 44.2 |
| PF | 0.86 |
| Tap Change Reading | 88390 |
| No of tap changing | 4 |
| Paste Level - E1 | 4.85 |
| Paste Level - E2 | 4.4 |
| Paste Level - E3 | 4.4 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 0 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 50 |
| Slipping - E2 | 100 |
| Slipping - E3 | 100 |
| CRO | Kelvin |
| Total No. of Batches | 19 |
| Plant 66kv kvah | 0 |
| Shift Incharge | Donald |