| Shift | B |
|---|---|
| Furnace | Furnace I |
| Date | 21 Mar 2026 |
| MWH | 31.4 |
| MVAH | 36.6 |
| PF | 0.85 |
| Tap Change Reading | 87722 |
| No of tap changing | 18 |
| Paste Level - E1 | 4.6 |
| Paste Level - E2 | 4.35 |
| Paste Level - E3 | 4.55 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 0 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 50 |
| Slipping - E2 | 100 |
| Slipping - E3 | 50 |
| CRO | Julius |
| Total No. of Batches | 12 |
| Plant 66kv kvah | (not set) |
| Shift Incharge | Ramesh |