Furnace I

ShiftB
FurnaceFurnace I
Date13 Feb 2026
MWH37
MVAH42.7
PF0.86
Tap Change Reading86596
No of tap changing24
Paste Level - E14.75
Paste Level - E24.6
Paste Level - E34.3
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E150
Slipping - E250
Slipping - E3100
CROSydney Kunda
Total No. of Batches15
Plant 66kv kvah(not set)
Shift InchargeAdinarayana