| Shift | C |
|---|---|
| Furnace | Furnace I |
| Date | 02 Feb 2026 |
| MWH | 37.4 |
| MVAH | 42.8 |
| PF | 0.87 |
| Tap Change Reading | 86216 |
| No of tap changing | 2 |
| Paste Level - E1 | 4.9 |
| Paste Level - E2 | 4.55 |
| Paste Level - E3 | 4.6 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 0 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 100 |
| Slipping - E2 | 100 |
| Slipping - E3 | 100 |
| CRO | Sydney |
| Total No. of Batches | 14 |
| Plant 66kv kvah | 115290 |
| Shift Incharge | Shrikanta |