| Shift | B |
|---|---|
| Furnace | Furnace I |
| Date | 21 Jul 2025 |
| MWH | 35.7 |
| MVAH | 41.5 |
| PF | 0.86 |
| Tap Change Reading | 84167 |
| No of tap changing | 0 |
| Paste Level - E1 | 4.8 |
| Paste Level - E2 | 4.8 |
| Paste Level - E3 | 4.5 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 1 |
| Casing Fitting - E3 | 1 |
| Slipping - E1 | 100 |
| Slipping - E2 | 100 |
| Slipping - E3 | 50 |
| CRO | Sydney kunda |
| Total No. of Batches | 17 |
| Plant 66kv kvah | 0 |
| Shift Incharge | Shrikanta |