| Shift | C |
|---|---|
| Furnace | Furnace II |
| Date | 17 Apr 2021 |
| MWH | 39.7 |
| MVAH | 47.3 |
| PF | 0.83 |
| Tap Change Reading | 12251 |
| No of tap changing | 22 |
| Paste Level - E1 | 4 |
| Paste Level - E2 | 4 |
| Paste Level - E3 | 4.05 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 0 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 50 |
| Slipping - E2 | 50 |
| Slipping - E3 | 50 |
| CRO | Kingfred |
| Total No. of Batches | 54 |
| Plant 66kv kvah | 223.42 |
| Shift Incharge | Shrikant |