| Shift | B |
|---|---|
| Furnace | Furnace I |
| Date | 05 Jul 2025 |
| MWH | 31.8 |
| MVAH | 38.4 |
| PF | 0.82 |
| Tap Change Reading | 83666 |
| No of tap changing | 20 |
| Paste Level - E1 | 5.1 |
| Paste Level - E2 | 4.7 |
| Paste Level - E3 | 5.1 |
| Casing Fitting - E1 | 1 |
| Casing Fitting - E2 | 0 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 0 |
| Slipping - E2 | 0 |
| Slipping - E3 | 100 |
| CRO | Sydney kunda |
| Total No. of Batches | 8 |
| Plant 66kv kvah | 0 |
| Shift Incharge | Shrikanta |