Furnace I

ShiftB
FurnaceFurnace I
Date22 Jun 2025
MWH15.1
MVAH17.9
PF0.84
Tap Change Reading83278
No of tap changing18
Paste Level - E14.45
Paste Level - E24.95
Paste Level - E35
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E10
Slipping - E20
Slipping - E30
CROSydney kunda
Total No. of Batches4
Plant 66kv kvah0
Shift InchargeAdinarayan