| Shift | B |
|---|---|
| Furnace | Furnace I |
| Date | 20 Jun 2025 |
| MWH | 36.8 |
| MVAH | 42.6 |
| PF | 0.86 |
| Tap Change Reading | 83193 |
| No of tap changing | 0 |
| Paste Level - E1 | 4.5 |
| Paste Level - E2 | 4.6 |
| Paste Level - E3 | 4.35 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 1 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 50 |
| Slipping - E2 | 100 |
| Slipping - E3 | 200 |
| CRO | Sydney kunda |
| Total No. of Batches | 16 |
| Plant 66kv kvah | 0 |
| Shift Incharge | Shrikant |