Furnace I

ShiftA
FurnaceFurnace I
Date05 May 2025
MWH37.4
MVAH42.5
PF0.88
Tap Change Reading82421
No of tap changing0
Paste Level - E14.2
Paste Level - E24.15
Paste Level - E34
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E150
Slipping - E2100
Slipping - E350
CROElisha
Total No. of Batches12
Plant 66kv kvah(not set)
Shift InchargeShrikanta