| Shift | C |
|---|---|
| Furnace | Furnace II |
| Date | 30 Apr 2023 |
| MWH | 36.6 |
| MVAH | 44.6 |
| PF | 0.82 |
| Tap Change Reading | 47976 |
| No of tap changing | 2 |
| Paste Level - E1 | 4.5 |
| Paste Level - E2 | 3.8 |
| Paste Level - E3 | 4.1 |
| Casing Fitting - E1 | 0 |
| Casing Fitting - E2 | 0 |
| Casing Fitting - E3 | 0 |
| Slipping - E1 | 100 |
| Slipping - E2 | 0 |
| Slipping - E3 | 100 |
| CRO | William |
| Total No. of Batches | 5 |
| Plant 66kv kvah | 225890 |
| Shift Incharge | Shrikant |