Furnace II

ShiftB
FurnaceFurnace II
Date29 Apr 2023
MWH34.9
MVAH41.7
PF0.83
Tap Change Reading47920
No of tap changing10
Paste Level - E14.6
Paste Level - E24.9
Paste Level - E35.2
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E10
Slipping - E2150
Slipping - E3150
CROLaston
Total No. of Batches18
Plant 66kv kvah(not set)
Shift InchargeVishinu