Furnace I

ShiftA
FurnaceFurnace I
Date11 Feb 2023
MWH34.9
MVAH42.1
PF0.82
Tap Change Reading63851
No of tap changing86
Paste Level - E14.25
Paste Level - E24.1
Paste Level - E33.9
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E150
Slipping - E2100
Slipping - E3100
CROEmmanuel
Total No. of Batches7
Plant 66kv kvah(not set)
Shift InchargeVishnu