Furnace I

ShiftA
FurnaceFurnace I
Date27 Nov 2022
MWH31.7
MVAH38.4
PF0.82
Tap Change Reading59532
No of tap changing55
Paste Level - E14.9
Paste Level - E24.1
Paste Level - E34.8
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E150
Slipping - E250
Slipping - E350
CROEmmanuel
Total No. of Batches30
Plant 66kv kvah0
Shift InchargeVishnu