Furnace I

ShiftA
FurnaceFurnace I
Date19 Oct 2022
MWH34.8
MVAH42.2
PF0.82
Tap Change Reading54438
No of tap changing7
Paste Level - E14.75
Paste Level - E24.85
Paste Level - E34.05
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E1150
Slipping - E2150
Slipping - E3150
CROLaston
Total No. of Batches44
Plant 66kv kvah(not set)
Shift InchargeVishnu