| Contract Number | SAFAL/P/MANGANESE ORE/02/2024/4 |
| Contract Date | 02 Feb 2024 |
| Type | Purchase |
| Supplier Name | Debansy Engineering Ltd |
| Description of Goods | Manganese Ore |
| Grade | Medium (38% - 44%) |
| Size | 10-90MM(MIN 90%) |
| Specifications | MN GRADE MIN BETWEEN 39%-41%,
AL2O3-4.04%
FE-4.5% MAX
SIO2-16% MAX
P-0.17% MAX
|
| Quantity | 5000 |
| Weight Unit | Metric Tonne |
| Destination | SAFAL PLANT KANONA |
| Rate | 55 |
| Currency | US Dollar |
| VAT % | 16 |
| Mode/Terms of Payment | Upon delivery at SAFAL plant and testing of the material |
| Terms of Delivery | DELIVERED KANONA PLANT SAFAL |
| Delivery Period | IMMEDIATE |
| Dispatch Through | SUPPLIER HIRED TRUCKS |
| Lot Number | Debansy Engineering Ltd -Mn Ore FY 2024 |
| Remark | 1 ALL TRUCKS SHOULD ACCOMPANY MINING LICENCE COPY/MINERAL TRADING PERMIT,COUNCIL LEVY AND POLICE CLERANCE CERIFICATE.ANY CHARGES RELATED TO THE SAID DOCUMENTS TO BE BORNE BY DEBANSY COMPANY.
2 MATERAIL ABOVE 41 % TO 43 GRADE THERE WILL BE PRORATE INCREASE IN PRICE WILL BE GIVEN,
3 MATERAL BELOW 39 % TILL 36% THERE WILL BE PRORATE DECREASE IN PRICEWILL BE GIVEN.
4 MATERIAL BELOW 36% WILL BE CONSIDERED AS REJECTED MATERIAL.
5 MINERAL ROYALTY TO BE PAID BY DEBANSY ENGINERRING COMPANY AND CERIFICATE TO BE FURNISHED BY DEBANSY ENGINERRING COMPANY TO SAFAL FOR RECORD..
|
| Other Reference(s) | PAYMENT WITHIN 48 HOURS TO 72 HOURS AFTER RECEIVING THE INVOICE. |
|---|