Furnace I

ShiftB
FurnaceFurnace I
Date27 Jan 2022
MWH37.9
MVAH45.8
PF0.82
Tap Change Reading10726
No of tap changing8
Paste Level - E14.2
Paste Level - E24.35
Paste Level - E34.25
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E31
Slipping - E150
Slipping - E250
Slipping - E350
CROLewis
Total No. of Batches60
Plant 66kv kvah(not set)
Shift Inchargeshrikanta