Furnace I

ShiftC
FurnaceFurnace I
Date24 Dec 2021
MWH16.2
MVAH18.6
PF0.87
Tap Change Reading6805
No of tap changing17
Paste Level - E10
Paste Level - E20
Paste Level - E30
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E10
Slipping - E20
Slipping - E30
CROJaphet
Total No. of Batches21
Plant 66kv kvah(not set)
Shift InchargeShrikant