Furnace I

ShiftC
FurnaceFurnace I
Date23 Oct 2021
MWH37.3
MVAH44.6
PF0.83
Tap Change Reading1917
No of tap changing51
Paste Level - E14.2
Paste Level - E24.2
Paste Level - E34.3
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E150
Slipping - E250
Slipping - E350
CROMartin
Total No. of Batches54
Plant 66kv kvah(not set)
Shift InchargeShrikanta