SAFAL/P/MN ORE/01.06/2022
| Contract Number | SAFAL/P/MN ORE/01.06/2022 |
| Contract Date | 17 Jan 2022 |
| Type | Purchase |
| Supplier Name | Danny C. Mwila |
| Description of Goods | Manganese Ore |
| Grade | High (44% - 50%) |
| Size | 20MM TO 200MM |
| Specifications | MN MIN 48% |
| Quantity | 1000 |
| Weight Unit | Metric Tonne |
| Destination | SAFAL PLANT KANONA |
| Rate | 1400 |
| Currency | Zambian Kwacha |
| VAT % | 0 |
| Mode/Terms of Payment | Upon delivery at SAFAL plant and testing of the material |
| Terms of Delivery | Delivered to kanona with documents including MRT |
| Delivery Period | Immediately |
| Dispatch Through | SUPPLIER HIRED TRUCKS |
| Lot Number | Danny C. Mwila - Mn Ore |
| Remark | |
| Other Reference(s) | one truck trial load to come first |
|---|
Total Supply: 0