Furnace II

ShiftB
FurnaceFurnace II
Date07 Oct 2021
MWH37.6
MVAH45.9
PF0.81
Tap Change Reading18011
No of tap changing26
Paste Level - E14.25
Paste Level - E24.5
Paste Level - E34.15
Casing Fitting - E10
Casing Fitting - E20
Casing Fitting - E30
Slipping - E150
Slipping - E2100
Slipping - E350
CROJulius
Total No. of Batches66
Plant 66kv kvah(not set)
Shift InchargeDonald